PROJECT ID

PROJECT LOCATION

PROJECT LIMITS

(project length)

PROJECT DESCRIPTION

RECOMMENDED FOR

FUNDING

% OF TOTAL FUNDING

ADDITIONAL NON-CITY FUNDING

(C: confirmed)

(P: pursue grants)

PROJECT ATTRIBUTES

East Ponce/Church St Sidewalks
 
 
 
Church Street from Erskine Rd to East Ponce de Leon Ave & East Ponce de Leon Ave from Church St. to approximately 500 feet east of the East Ponce de Leon/ Brockett Road intersection (bus stop across from Tahoe Village Shopping Center)
(1700 feet)
Construct 5 foot sidewalks including a sidewalk crossing at CSX RR, new granite header, new ADA ramps, paint four (4) crosswalks with corresponding signage, two pedestrian push button poles/signal heads, safety fencing to discourage pedestrian crossing of the RR right-of-way, and concrete pads at four MARTA bus stops
$800,000
6.8
$120,000
(C)
Dirt paths exist on back of curb due to heavy pedestrian use
Wheelchair bound pedestrians observed on road
No sidewalks exist currently within scope of work
Dirt pads at bus stops
Montreal Rd.  Pedestrian Improvements
 
 
Montreal Rd from Clarkston Industrial Blvd. to approximately Hill St.
(1600 feet)
New crosswalk - pedestrian bus stop pad and ramp - pedestrian crossing signal adjacent to Avalon Park apartments, various sidewalk and driveway reconstruction including striping within project limits to meet ADA standards
$250,000
2.1
$0.00
Sidewalk and driveway ramps are not ADA accessible on corridor
ADA accessibility at bus stop required
Market Street
Sidewalks
 
City Annex to Market Crossing subdivision entrance
 
(3100 feet)
New sidewalk on east and south side of Market Street (one side only) includes power pole/water meter & valve relocations, driveway reconstructions, retaining wall and landscape replacement; temporary easement acquisitions anticipated
$700,000
6.0
LMIG
(C)
Sidewalks do not exist on Market Street
Pedestrians must use street to walk to downtown Clarkston