The City of Clarkston is moving forward with a street resurfacing project to improve road conditions throughout the community. Please review the schedule below to see when work will take place in your area.
Resurfacing work will be completed in a single day unless otherwise noted.
Temporary road closures and detours may occur.
Residents and businesses are encouraged to plan accordingly.
Dates are tentative and are subject to change.
Street Name | To | From | Start Date | Finish Date |
|---|---|---|---|---|
Tribble Street | Clark Street | Dead End | February 24 | February 24 |
Lincoln Street | Smith Street | Clark Street | February 24 | February 24 |
Clark Street | Smith Street | Dead End | February 25 | February 25 |
Lester Street | Clark Street | Smith Street | February 26 | February 26 |
Smith Street | Lincoln Street | Montreal Street | February 26 | February 26 |
Sams Road | Montreal Road | Hill Street | February 27 | February 27 |
West Hill Two | Hill Street | Sams Road | February 28 | February 28 |
West Hill One | North Indian Creek | West Hill Street | March 3 | March 3 |
Casa Woods Lane Two | Casa Drive | Cul-de-sac | March 4 | March 4 |
Casa Woods Lane One | Casa Drive | Cul-de-sac | March 4 | March 4 |
Jolly Avenue North | East Ponce de Leon Avenue | Mell Avenue | March 7 | March 11 |
Orchard Street | Jolly Avenue | Pecan Street | March 12 | March 12 |
Pecan Street | East Ponce de Leon Avenue | Jolly Avenue | March 13 | March 14 |
Lovejoy Street | Rowland Street | Church Street | March 17 | March 17 |
Jolly Avenue South | Rowland Street | City Limits | March 17 | March 17 |
Maclaren Drive | Market Street | Dead End | March 18 | March 19 |
Cleavemark Drive | Norman Road | Dead End | March 20 | March 21 |
Clydedale Drive | Crandford Drive | Cleavemark Drive | March 24 | March 25 |
Cranford Drive | Rogers Street | Cleavemark Drive | March 26 | March 26 |
For updates and additional information, please visit www.clarkstonga.gov.
Thank you for your cooperation as we work to enhance Clarkston’s roadways.